Reconstruction and construction of a school, Otradny Avenue, 36V

Servite Group completed general construction work on the school building renovation, including:
• strip foundation;
• wall erection and roof installation;
• internal partitions, ceilings, and floors;
• utility installation – electrical, water, and heating utilities;
• fire and security alarm installation;

• landscaping;

• construction of sports grounds with rubber surfaces and exercise equipment;

• finishing work.
The project is currently underway. The following work is planned for the near future:
• asphalt paving;
• installation of outdoor lighting.